Date: June 8, 2025 (Sunday)
Estimated Time of Shutdown: 8:00 AM
Estimated Time of Restoration: 5:00 PM
Affected Areas/Municipalities:
π San Jose
π Dinagat
π Cagdianao
π Basilisa
π Libjo
Reason for Plant Shutdown:
π Installation of Neutral Earthing Transformer
π Installation of Disconnecting Switch
DIELCO Ride-on Activities:
π Replacement of rotten pole C7/C7 structure at Sitio Busay, New Mabuhay, Dinagat.
π Upgrading of distribution line from Single Phase to Vee Phase at Poblacion, Cagdianao.
π Replacement of rotten pole C8 structure at San Jose, Libjo.
π Re-structure from C4 to C8 structure due to low vertical clearance at Llamera, Libjo.
π Retightening of Sub-Feeder Recloser at Bolodbolod, Gen. Aguinaldo, Libjo and DIELCO Main Office, Justiniana, San Jose.
We are sorry for the inconvenience and thank you for your understanding.
DIELCO MANAGEMENT